lusion® Level Entry Base Installation
  12
  Mark outline of base on timber floor.
Cut out 20mm flooring and remove.
Glue PVC Flange to drain. Install tile & slate, ensuring 6mm clearance around LM flange. Install Gib/Villa board walls to bottom of rebate
 4
  20mm Flooring
Rebate
     5
      IMPORTANT
Gib/Villa Board to be installed prior to base installation
Install 20mm marine ply or compressed sheet. Glue and screw into position.
Concrete Floor - Mix tile adhesive and apply with trowel into rebated base area. 8 hour cure time (adhesive kit included).
Install lusion® base and weigh down with adhesive pail filled with water.
  6b
8hrs
Tile
Adhesive Concrete
Floor
    7
 